Splash Pad
Project Summary
Nixa Parks and Recreation is Adding a Splash Pad!
Status
Project Quick Facts
Budget:
$650,000.00
Contractor:
Branco Enterprises Inc.
Anticipated Completion Date:
April 30, 2025
Status
We are thrilled to announce that Nixa Parks and Recreation is expanding our amenities with the construction of a brand-new Splash Pad, located next to the Aquatics Center on the west side. This long-requested feature will provide fun and refreshing opportunities for the community.
The project is funded through Impact Fees that have been saved for a new development of this scale. The splash pad construction has begun and will continue into the fall, with an expected opening in May 2025. Stay tuned for updates as the construction work progresses! We cannot wait for the community to enjoy this exciting new amenity next year!
October 10, 2024
Splash Pad Update
Construction continues on the new splash pad at McCauley Park. Crews have completed the majority of the dirt work, and have begun pipe installation for the pump and filtration area and the gravel base layer for what will be the splash pad itself. The project continues to move along as scheduled.Â
September 24, 2024
Clearing & Excavating
Branco is working on site clearing and excavating for the splash pad.
September 19, 2024
Splash Pad Site Clearing
Branco has started working on clearing the site for the splash pad.
 Â