Nixa City Hall Remodel

Project Summary

Nixa City Hall is undergoing renovations to address customer service, security, staff capacity, and event opportunities.

Project Quick Facts

Budget:

$2.2 million for city hall renovations, which will include the moving of Utility Billing Staff into City Hall, renovating office space for future growth, moving the front entrance for updated security, and renovation to Council Chambers to maximize event space and opportunities.

Contractor(s):

Hambey Construction

Completion Date:

July 2026

Nixa City Hall is undergoing renovations to address customer service, security, staff capacity, and event opportunities. The renovations will:

  • Move Utility Billing staff & functions from its existing building into City Hall at the westmost entrance.
  • Move Front Reception from the Council Chambers Entrance to the second eastmost entrance.
  • Update security measures within City Hall.
  • Expand Council Chambers to provide more flexibility with the space.
  • Add additional office space to address staff capacity and expansion needs.

February 2, 2026

Phase III

Admin staff has moved into the new Phase II offices to allow for Phase III to begin. Phase III will include a new conference room, updated City Council Chambers, the addition of two offices for legal, an office for the mayor, and renovations of all other existing offices.

Planning & Zoning meetings have been moved to the Police Station and City Council meetings have been moved to the Fire Department Training Facility while council chambers is undergoing renovations.

 

January 8, 2026

Phase I / Phase II

Phase I is complete and is acting as the temporary entrance to City Hall on the westmost side of the building. The new breakroom has been completed and minor work on Phase II remains.

December 16, 2025

Phase II Work

Planning & Development Staff has moved into Phase 1 to accommodate construction of new offices.

September 18, 2025

Construction Update

Phase 1 continues to get painted and flooring is finished up.

September 4, 2025

Construction Update

Flooring is added to Phase 1 Offices.

August 29, 2025

Construction Update

Phase 1 walls are prepped and painted.

August 14, 2025

Sheet Rock Added

Phase 1 moves forward quickly as new areas get sheetrock.

August 7, 2025

Framing

Areas have been framed to accommodate new offices and areas as designed.

July 24, 2025

Sprayfoam Insulation

Hambey Construction has added spray foam insulation to the old portion of the building, constructed in the early 1990’s, which should provide much needed improvements while also improving efficiency.

July 10, 2025

Construction Update

Crews have been demolishing areas within Phase 1 (Old Court Area, Finance Offices, Communications Offices,  and Human Resources Offices) to prepare for remodel work.

June 25, 2025

Council Approval

Council has approved a contract with Hambey Construction not to exceed $2.2 million in the remodel of City Hall