Milton Electric Improvements

Project Summary

This project will address system reliability and safety in an area where aging wire has failed. This project will start on Park Street and continue north to Northview along Milton Drive.

Project Quick Facts

Budget:

$159,174.34

Contractor:

BBC

Anticipated Completion Date:

Project completion will be approximately six weeks from May 25th, weather permitting.

This addresses one of the Electric Department’s priorities for 2026, which aims to address aging electric infrastructure to improve system reliability and address safety concerns.

May 22, 2026

Project Start Date

This project is anticipated to start on May 25th and have a construction window of approximately six weeks.