Kelby Creek Phase 4

Project Summary

This subdivision will will be split into a Phase 4A and a Phase 4B. 4A will feature 21 buildable lots in the Kelby Creek Subdivision.

Developer:

SNB, LLC.

Phase 4A features 21 buildable lots, with additional lots available in a future phase.

April 26, 2025

Kelby Creek 4A Construction

Kelby Creek 4A features 21 buildable lots. Infrastructure has been put in place. Site has seed & straw.

October 24, 2024

Pre-Construction Meeting Held

Willow Brook plans have been approved and a preconstruction meeting has been held. Crews can start construction.

February 26, 2024

Phase 4

Phase 4 is under review. This phase will consist of 78 single-family residential lots.

Photo shows a field where Meadowbrook Phase 4 will be built

February 26, 2024

Phase 3

Meadowbrook Phase 3 has a final plat recorded with the City of Nixa. Construction of houses anticipated to begin soon.

Photo shows empty lots waiting for the construction of homes. Roadway infrastructure is fully built-out.

June 7, 2023

Construction Underway

With phases 1 and 2 complete, construction on homes has begun.