Water Tower Projects
Project Summary
On this page, we will provide updates on all water tower repainting projects.
Project Quick Facts
Project Overview:
Water Tower #1 is located on St. Louis Street in downtown Nixa. This is Nixa’s first water tower; therefore, it contains numerous layers of old paint, including some layers of lead-based paint. In order to repaint the tower on the inside and outside, the whole tower will need to be tented and the lead-based paint removed.
Budget:
$250,000
Contractor(s):
TBD
Anticipated Completion Date:
Spring 2024


The department maintains 10 water wells which provide drinking water to the city’s water grid, and 8 water towers which maintain water pressure across the system. On this page, we will provide updates on all water tower repainting projects.
June 5, 2023
Water Tower #1 Update
Planning for this project is complete, and bids go out to contractors this week.